Start with the concrete
Dense, well-compacted, properly cured concrete is the first barrier. A water-reducing admixture such as Tac 501 lowers the water-cement ratio and makes the concrete less permeable.
Add integral waterproofing
An admixture such as TAC 07 is mixed into the concrete to help protect against water seepage.
Treat the joints
Most leaks occur at construction joints. A hydrophilic waterstop like Swell Bar is fixed in the joint before the next pour and swells to seal it.
Finish with good practice
Cure the concrete, avoid honeycombing, and follow the manufacturer data sheet for every product.
Checklist for a water-tight structure
Use a low water-cement ratio, compact thoroughly, cure properly, seal every construction joint, and avoid cold joints. Plan joint positions before the pour.
Admixture or coating?
Read integral waterproofing vs coating and hydrophilic vs PVC waterstop to choose your system.
Products used
TAC 07, Tac 501 HR and Swell Bar are available from SHAH Trading. See all construction chemicals.